Parkland Development Project
24016 12th Street
Trempealeau, WI 54661
Project Progress Report: Construction!
Construction began on June 24th, with crews from Ayres and Stout surveying the area for clearing and grubbing.
Grading, installation of water and sewer mains, retention ponds, and base courses for trails, sport courts, and baseball fields were all completed before winter. Posts for fencing and backstops were installed during the winter months.
Major Construction Resuming in 2025
Schedule is subject to change.
Park Site Improvements
Asphalt trail and court paving were completed during the first week of June 2025. Installation of chain link fencing and site landscaping is scheduled to begin on June 9th, 2025. Court surfacing, native seed mixes, court striping, and park amenities such as benches, bike racks, and tables will follow through July. Parking lot work, including fine grading, concrete paving, and asphalt binder course, is set to begin in September. Final pavement markings and punch list work will conclude by mid-September.
Field Improvements
Irrigation installation, dugouts, and field surfacing are planned for June. Additional details, including sports field seeding and synthetic turf installation, are expected to wrap up in early September 2025.
The original substantial completion date was July 16th. Due to change orders related to donations to the Village for the park, including converting the east field to synthetic turf and enhancements to the pickleball courts, the new proposed substantial completion date is September 19th, 2025.
Background
- Land was purchased in 2014 with a combination of County grant funds and local funds with the goal to build a park – the need for a park was outlined in the resolution.
- Continued development of parks and recreational facilities are heavily emphasized in the comprehensive plan public feedback.
- The Village has consistently received public pressure to follow through with this project and has also heard from community members and employees that there is a real need for more baseball and soccer fields.
Park Project
- The current proposal is for the Village to commit $3M for the initial phase of the project which includes the following items:
- Two Ball Fields – Softball and Baseball (bleachers, dugouts, fencing)
- Two Pickleball Courts
- One Basketball Court
- Grading and seeding the northeast corner for a large event area/soccer fields
- Roadway and utility extensions
- Parking Lot
- Lighted Nature Trails
- Retention Pond
Donations
- Donations are always welcome and can be specified for certain projects.
- click the link below to make a one time or recurring donation to our community park
- donations are being managed by the non profit Winona Community Foundation
- if you’d like to sponsor a specific project, please let us know!